| NO | TANGGAL | URAIAN | DEBET | KREDIT | SALDO |
|
| 1 |
| Kas panti | 160,000,000 |
| 160,000,000 |
|
| 2 | | Beli sirtu |
| 885,000 | 159,115,000 |
|
| 3 | | besi 400 x 7000 x
19kg |
| 53,200,000 | 105,915,000 |
|
| 4 | 19/01/12 | tanah uruk 10 truk |
| 2,250,000 | 103,665,000 |
|
| 5 |
| besi 8x100,10x100,12x50,bendrat20kg |
| 6,110,000 | 97,555,000 |
|
| 6 |
| bata 10.000 bj |
| 4,700,000 | 92,855,000 |
|
| 7 |
| tanah uruk 10 truk kecil |
| 2,400,000 | 90,455,000 |
|
| 8 | | tenaga uruk |
| 330,000 | 90,125,000 |
|
| 9 | 30/01/12 | UM semen 200 sak |
| 6,000,000 | 84,125,000 |
|
| 10 |
| pasir dan bata |
| 4,100,000 | 80,025,000 |
|
| 11 | 4/2/2012 | bayar tukang |
| 4,000,000 | 76,025,000 |
|
| 12 | | kusen pintu 3 buah |
| 4,350,000 | 71,675,000 |
|
| 13 | 8/2/2012 | jendela |
| 3,600,000 | 68,075,000 |
|
| 14 |
| sisa bayar semen 200 sak |
| 1,125,000 | 66,950,000 |
|
| 15 |
| sirap randu 6000x200 |
| 1,200,000 | 65,750,000 |
|
| 16 | 19/02/12 | pasir |
| 3,750,000 | 62,000,000 |
|
| 17 |
| 12 dumtruck X 750.000 |
| 9,000,000 |
|
|
| 18 |
| ongkos krj tahap 3 |
| 2,500,000 |
|
|
| 19 |
| ongkos krj tahap2 |
| 2,000,000 |
|
|
| 20 |
| koral 1 truck |
| 900,000 |
|
|
| 21 | 24/02/12 | sirtu |
| 3,750,000 |
|
|
| 22 |
| kayu sirap10bendel 3x4,10bendel4x6 |
| 2,830,000 |
|
|
| 23 | 26/02/12 | bayar tukang |
| 5,060,000 |
|
|
| 24 | 27/02/12 | sirtu |
| 5,250,000 |
|
|
| 25 | 28/02/12 | koral+ timba |
| 5,270,000 |
|
|
| 26 |
| bata 7000 bj |
| 3,290,000 |
|
|
| 27 | 5/3/2012 | kerikil |
| 950,000 |
|
|
| 28 | 7/3/2012 | UM besi 10x200 |
| 7,000,000 |
|
|
| 29 |
| bayar tukang |
| 11,500,000 |
|
|
| 160,000,000 |
|
|
|
MATERIAL YANG MASIH DIPERLUKAN
| NO |
URAIAN |
SATUAN HARGA |
TOTAL |
| 1 |
Besi ø 10 X 350 |
58,000 |
20,300,000 |
| 2 |
Besi ø 8 X 100 |
32,000 |
3,200,000 |
| 3 |
Triplek 1cm X 130 |
78,000 |
10,140,000 |
| 4 |
Semen molen 34m3 |
62,000 |
21,080,000 |
| 5 |
Bambu 2000 Biji |
4,500 |
9,000,000 |
| 6 |
Kayu Glugu 6X6X200 batang |
20,000 |
400,000 |
| 7 |
Ongkos tukang kurang |
10,000,000 |
10,000,000 |
| 8 |
Paku 60 Kg |
11,000 |
660,000 |
| 9 |
Bendrat 20Kg |
15,000 |
300,000 |
| 10 |
Ongkos tukang Cor Lantai II |
15,000,000 |
15,000,000 |
| |
90,080,000 |
| |